Public Record Brighton Red Barn Cattle Dip Vat
Public Record Brighton Red Barn Cattle Dip Vat (CDV) Table
The Seminole Tribe of Florida has defined the stages of cleanup as follows:
Stage Zero: Identification of a possible brownfields site
Stage One: A phase one assessment has been preformed on the possible site which involves a historical investigation.
Stage Two: A phase two site assessment has been preformed using site characteristics and conditions and sampling and data analysis to determine the contaminant.
Stage Three: The physical clean-up of the site, which may include but is not limited to soil and/or water.
Stage Done: The site is clean and ready for further use.
| Site Name | Brighton Red Barn CDV |
| Type of Site | Cattle Dip Vat |
| Size of Site (in acres) | 1 |
| Site Location (Street name, City, State, Zip) | Glades County, Florida |
| Latitude/Longitude | 27º04'21.6" north / 81º06'54.9" west |
| Name of Owner | The Seminole Tribe of Florida |
| Stage of Cleanup | Stage Three - Water cleanup remains |
| Date Stage Started | |
| Expected date stage completion | |
| Nature of contaminant and name (if applicable) | Arsenic |
| Summarize nature of contamination at site | Seepage into soil and/or groundwater from previous usage |
| Is Institutional Control in place? (Y/N) | None |
| Type of Institutional Control | None |
| EPA funding spent to date at site |
Institutional Controls
| Activity | During this reporting year | Cumulative |
| Number and frequency of oversight audits of clean-ups certified by licensed site professional | None | None |
| Number and frequency of state/tribal oversight audits conducted | None | None |
| Number of sites where staff conducted audits, provided technical assistance, and conducted other oversight activities | None | None |
| Number of staff conducting oversight audits, providing technical assistance, and conducting other oversight activities | None | None |